Building Update: Pillars and Beams

A lot has happened in the last month at 4949 E Eastman Ave!  The drain lines and water lines were installed and roughed in, and the bed was prepared to receive the slab.  Periodic snows slowed the work some, but our construction company took advantage of any opportunity and on March 22, the slab was finally poured.

The same day, the outer pillars were set in place.  Then the building of the structure itself began in earnest.

We praise God for the progress that is being made toward the completion of our new church building.  It’s exciting to see it taking shape at long last.  In the next few weeks, its looks will change dramatically as walls and roof are added.

“I was glad when they said to me, “Let us go to the house of the Lord!” Psalm 122:1